Eni Coral South FLNG
•Award Contract
•$7 billion investment
Eni MAMBA
•FID expected 2018

Anadarko
Mozambique LNG 1
•FID expected 2018
|
Tanzania LNG Plant
•Pre-FEED expected
2017/2018 End
•$30 billion investment
Dar es Salaam to Tanga and on to Mombasa gas
pipeline project
•Feasibility Study
•558-km |
Kudu gas to power project
•885MW CCGT Power Station
XARIS Walvis Bay LNG Terminal & Power Plant
•250MW
•LNG import from USA, Egypt and West Africa |
SACOIL African Renaissance
Pipeline Project
•Feasibility study
•$6 billion

Coega& Richards Bay LNG Terminal and LNG to Power
•First Phase Bidding
•$3.7 billion |